Math Is Fun Forum

  Discussion about math, puzzles, games and fun.   Useful symbols: ÷ × ½ √ ∞ ≠ ≤ ≥ ≈ ⇒ ± ∈ Δ θ ∴ ∑ ∫ • π ƒ -¹ ² ³ °

You are not logged in.

#1 2006-11-24 08:20:25

Neha
Member
Registered: 2006-10-11
Posts: 173

fred/barney

fred can complete 5 jobs in 4 hours
when barney helps him, they can complete 9 jobs in 6 hours
how long would it take barney to complete 1 job

ok i think this is wrong but you tell me :

9/6 = 1/x
9x = 6
x = 6/9
x = 2/3
x = 0.6

help


Live Love Life

Offline

#2 2006-11-24 09:53:32

MathsIsFun
Administrator
Registered: 2005-01-21
Posts: 7,711

Re: fred/barney

fred = 5/4 jobs/hr
fred + barney = 9/6 jobs/hour

so

barney = 9/6 - 5/4 = 6/4 - 5/4 = 1/4 jobs/hr

So barney would take 4 hours to complete a job. Sack him.


"The physicists defer only to mathematicians, and the mathematicians defer only to God ..."  - Leon M. Lederman

Offline

Board footer

Powered by FluxBB