need answer to the question

if a job is done by 3 worker in 21 days , then how many days it will take for 7 workers, if all the other conditions are remain same.

#2 2009-10-07 22:23:51

bobbym
bumpkin
From: Bumpkinland
Registered: 2009-04-12
Posts: 109,606

Re: need answer to the question

Hi Abhishek Gijare;

Each day 1 worker does 1 / 3 * 1 / 21 = 1 / 63 of the job. 7 workers do 7 / 63 = 1 / 9 of the job each day. So it will take them 9 days.

Or:  21 / (7 / 3) = 9