if a job is done by 3 worker in 21 days , then how many days it will take for 7 workers, if all the other conditions are remain same.
Hi Abhishek Gijare;
Each day 1 worker does 1 / 3 * 1 / 21 = 1 / 63 of the job. 7 workers do 7 / 63 = 1 / 9 of the job each day. So it will take them 9 days.
Or: 21 / (7 / 3) = 9