fred can complete 5 jobs in 4 hours
when barney helps him, they can complete 9 jobs in 6 hours
how long would it take barney to complete 1 job

ok i think this is wrong but you tell me :

9/6 = 1/x
9x = 6
x = 6/9
x = 2/3
x = 0.6

help


Live Love Life

Offline

#2 2006-11-24 09:53:32

MathsIsFun
Administrator
Registered: 2005-01-21
Posts: 7,713

Re: fred/barney

fred = 5/4 jobs/hr
fred + barney = 9/6 jobs/hour

so

barney = 9/6 - 5/4 = 6/4 - 5/4 = 1/4 jobs/hr

So barney would take 4 hours to complete a job. Sack him.